Construction Work

Current work in progress

At the moment, the four-storey building is being erected. Throughout all activities, special care will be taken to minimize ground vibrations, ensuring the safety of both people and animals.

Attention: Deliveries to the HIRI site and other construction work on the medical campus may result in debris on traffic routes.

 

Construction Work Schedule

2023

December: Construction of the building shell begins

August: Start of excavation of the construction pit and implementation of the shoring

July: Start of construction

July: Groundbreaking ceremony

April: Preliminary infrastructure works

2022

December: Application for project funding

August: Construction permit

May: Design planning completed

2021

May: Demolition of the former Urology Department at the future HIRI site on the Medical Campus Würzburg

2020

May: Pre-planning completed

2019

July: Leasehold agreement

2018

December: Commissioning doranth post architekten, work phase 1 — 8

October: 1st prize: doranth post architekten

March: Architectural competition

2017

November: Coordination talks

May: Cooperation agreement with UKW

2016

November: Resolution of the Supervisory Board